Highway
Highway is an integrated kerb and high capacity linear drainage
system, offering a cost-effective all-in-one alternative to
conventional kerb, gully and drain networks.
Style & appearance
| Photographs |
 |
| Product photograph |
 |
| Accessory units |
 |
 |
Highway Shallow Base Unit
(for use in areas with restricted depth) |
Deep Base Unit
(for extra capacity) |
 |
 |
Base Unit
with concrete drainage top |
Crossing Base Unit
(galvanised steel plate) |
 |
 |
Silt Box Top / Cover 01460
(ductile iron) |
External Radius Unit
Also available:
internal radius (dotted) |
 |
 |
Junction Unit
(two units form junction) |
Combined Outlet
Junction Unit |
 |
 |
Outlet Units
(two units form outlet) |
Cable Duct Unit |
 |
|
Base Unit
with Ductile Iron Grid 01604 (Class D400 and E600) |
|
Product data
Trafficking
- Highways
- Commercial sites
- Industrial sites
- Access roads
Features and benefits
- Integrated kerb and high capacity linear drainage system
- Dramatically reduces the need for expensive underground piping
and cost of excavation
- Requires only simple kerb-laying installation (no added
underground pipework)
- Multiple inlet holes along the length of kerb remove water
immediately from the road surface
- Large capacity channel stores and removes water to an outlet,
removing the need for frequently placed gully grates
- Cost effective compared to other combined kerb and drain
systems
- Supplied in pallet packs for easy maneuverability on site
- Packed to suit manual handling
Main units dimensions
| Dimensions (mm) |
Base unit |
Top unit |
| Length |
400 |
400 |
| Width (overall) |
460 |
460 |
| Depth (overall) |
369 |
245 |
Available from stock and supplied in pallet
packs: (base) 16 units and (top) 8 units
Channel dimensions 300x300 mm (approx.)
Inlet dimensions 65 x 150 mm ellipse (approx.).
Accessory units dimensions
| Accessory |
Length (mm) |
Depth (mm) |
Width (mm) |
availability |
| Deep base unit |
440 |
400 |
460 |
to order |
| Shallow base unit |
400 |
222 |
460 |
to order |
| Crossing base unit |
400 |
310 |
460 |
from stock |
| Base outlet unit |
400 |
369 |
460 |
from stock |
| Crossing base plate |
400 |
12.5 |
460 |
from stock |
| Base junction unit |
400 |
369 |
460 |
to order |
| Base unit with ductile iron grid |
400 |
419 |
460 |
from stock |
| Base unit with concrete drainage top |
400 |
504 |
460 |
to order |
| Silt box top cover |
400 |
245 |
460 |
from stock |
| Cable duct unit |
400 |
245 |
460 |
from stock |
| Combined base junction/ outlet unit |
400 |
369 |
460 |
to order |
| Shallow base outlet |
400 |
222 |
460 |
to order |
| Deep base outlet |
400 |
444 |
460 |
to order |
| Bolted access for use with ductile iron grid |
– |
– |
– |
to order |
| Crossing base unit bend |
– |
– |
– |
to order |
| Textured top unit option |
– |
– |
– |
to order |
| Painted top unit option |
– |
– |
– |
to order |
| Porous asphalt top unit option |
– |
– |
– |
to order |
Radius units: 25/11, 10/8, 7/6 metre versions,
for external radii.
Radius half units available for internal radii in same sizes.
Design considerations
Description
A drainage system with multiple inlet holes along full kerb
length, available in both half batter and splay profiles. The
U-shaped channel has a cast-in recess for sealing mastic.
Composition and manufacture
Highway is manufactured from high quality granites and quartzite
using both wet pressed and semi dry processes.
Complementary products
British Standard Kerb.
Loading standards
Conforms to EN 1433 Class D. (Class D=400kN: Public highways and
general parking areas).
Performance
Strength
Meets requirements of BS EN 1433.
Specification clauses
Assistance with model specification clauses is available for
this product,
please refer to Charcon Technical Services.
Colour availability
Standard
Basic components
Two-part kerb comprising:
- Base unit: high capacity channel.
- Top unit: soffit for channel – incorporating semi-elliptical
inlets.
- Splay and Half Battered options available.
General Principles
The aim is to ensure prompt and cost-effective removal of
surface water during and immediately after rainfall.
Multiple inlet holes and the continuous U-shaped channel profile
enable system design which minimises underground pipework. This can
provide a lower-cost solution than traditional gully systems.
System capacity
For Highway drainage, identify any flow constraints in advance,
including:
- vehicular crossings requiring crossing base units
- tight radii*
- junction units creating turbulent flow*
- outlet unit capacity
- outfall chamber/pipe capacity
- linear grates
Note:
*Hydraulic properties given in tables are conservative and so, in
most cases, any flow reductions arising from these factors may be
ignored in design.
In common with all combined kerb and drainage systems, Highway
top and base units will NOT run full due to turbulence from the
inlet holes. System flow capacities, given in the table below, are
therefore confined to realistic flow levels rather than
theoretical/full bore maximum levels.
Capacities vary according to type of base unit installed in the
system, (standard, shallow, deep or crossing base units – see table
below).
Note
Capacity will be reduced over time wherever there is a likelihood
of a significant build-up of silt.
Highway system flow capacities
| |
Shallow base unit |
Standard base unit |
| Gradient |
Vel. m/sec |
Dis. l/sec |
Vel. m/sec |
Dis. l/sec |
Vel. m/sec |
Dis. l/sec |
Vel. m/sec |
Dis. l/sec |
| 1:50 (2.00%) |
1.9 |
39 |
2.3 |
97 |
2.6 |
171 |
2.7 |
236 |
| 1:100 (1.00%) |
1.3 |
28 |
1.6 |
69 |
1.9 |
120 |
1.9 |
166 |
| 1:200 (0.50%) |
0.9 |
20 |
1.1 |
48 |
1.3 |
85 |
1.4 |
117 |
| 1:300 (0.33%) |
0.8 |
16 |
0.9 |
39 |
1.1 |
69 |
1.1 |
95 |
| 1:400 (0.25%) |
0.6 |
14 |
0.8 |
34 |
0.9 |
60 |
1.0 |
83 |
| 1:500 (0.20%) |
0.6 |
12 |
0.7 |
30 |
0.8 |
53 |
0.9 |
74 |
| 1:1000 (0.10%) |
0.4 |
9 |
0.5 |
21 |
0.6 |
37 |
0.6 |
52 |
| |
Deep base unit |
Crossing base unit |
| Gradient |
Vel. m/sec |
Dis. l/sec |
Vel. m/sec |
Dis. l/sec |
Vel. m/sec |
Dis. l/sec |
Vel. m/sec |
Dis. l/sec |
| 1:50 (2.00%) |
2.8 |
244 |
2.9 |
310 |
2.4 |
115 |
2.6 |
178 |
| 1:100 (1.00%) |
2.0 |
172 |
2.0 |
219 |
1.7 |
81 |
1.8 |
126 |
| 1:200 (0.50%) |
1.4 |
121 |
1.4 |
154 |
1.2 |
57 |
1.3 |
89 |
| 1:300 (0.33%) |
1.1 |
99 |
1.2 |
126 |
1.0 |
46 |
1.1 |
72 |
| 1:400 (0.25%) |
1.0 |
85 |
1.0 |
109 |
0.8 |
40 |
0.9 |
62 |
| 1:500 (0.20%) |
0.9 |
76 |
0.9 |
97 |
0.8 |
36 |
0.8 |
56 |
| 1:1000 (0.10%) |
0.6 |
54 |
0.6 |
68 |
0.5 |
25 |
0.6 |
39 |
Key: Vel. = velocity, dis. = discharge
Inlet capacity
The capacity of each inlet, maximised when first laid, can be
affected by future re-surfacing which may raise carriageway levels
above the normal 125 mm kerb-face. If so, capacity can be protected
by cutting back the surfacing adjacent to each inlet (special tool
available).
Outlet capacity
In practice, capacity requirements can vary according to
location of the outlet and the depth of flow within the system. For
design purposes, an outlet capacity of 62 mitres per second should
be adopted. If this capacity is insufficient, more than one outlet
unit should be installed to discharge into the outfall chamber.
Outfall chamber/pipe capacity
Outfall discharge capacity should be as large as possible to
ensure benefits from Highway system. In large schemes, gully pots
used as outfall chambers may be insufficient because turbulence can
reduce capacity levels below that which a standard 150 mm outfall
pipe can sustain. Where possible, purpose-built chambers (brick or
precast manhole rings) are recommended instead to help minimise
effects of turbulence on capacity. The appropriate outfall pipe can
then be selected to suit the specific case (see table below).
Linear grates Highway can be used for long runs
of linear drainage where high volumes of surface water drainage is
required or high wheel loads are imposed.
Highway outfall pipe capacity
| Gradient |
Pipe diameter (mm) |
| 1:20 (5%) |
42 |
122 |
260 |
468 |
736 |
| 1:40 (2.50%) |
29 |
86 |
183 |
330 |
534 |
| 1:60 (1.67%) |
24 |
70 |
149 |
268 |
436 |
| 1:80 (1.25%) |
20 |
60 |
129 |
233 |
376 |
| 1:100 (1.00%) |
19 |
54 |
116 |
208 |
337 |
Installation design – units
General principles
All units are unreinforced: protect from stresses caused by
thermal expansion of cementitious paving materials. Leave 1mm gap
between each unit to prevent damage from thermal expansion of the
units themselves.
Expansion joints MUST be installed on each side of drainage runs
in concrete pavements or those incorporating a cement bound/lean
mix concrete roadbase.
DO NOT place these joints directly adjacent to any trafficked
unit as this would allow units to rock under trafficking and may
allow water ingress into the base or sub-grade.
- Recommended position of joints
(minimum distances):
- 600 mm from Clearway/Safeticurb units (see Figs 12-14).
- 125 mm from Highway units (see Figs 5-6).
Note:
As Highway units are not regularly trafficked, expansion joints
could be placed directly against them. However, 125 mm distance is
recommended to avoid ingress of water between the unit and
carriageway construction.
Base foundations
Recommended typical foundations are:
- for Clearway/Safeticurb: minimum 150 mm depth of ST4 concrete
with a 25 mm bed of Class 1 mortar (1:3 cement: sand) to allow easy
adjustment of units to line and level.
- for Highway: minimum 75 mm of concrete.
Note:
Strength, overall depth and width of the base may need to be
increased when laid on low - strength sub-grades.
Haunching
Recommended typical haunches (to within 100 mm of top unit)
are:
- For Clearway/Safeticurb: ST4 concrete.
- For Highway: ST1 concrete minimum 125 mm width.
General principles
Details of outlet units an inspection access differ according to
which linear drainage system is used.
In any system, silt or detritus should normally be prevented from
entering the main drainage sewer. An outfall chamber is required to
enable silt collection before onward connection to a sewer.
Types of outfall chamber
- trapped precast concrete, clay or plastic gully pots. Gully pot
capacity may be insufficient for some largerlinear drainage
installations.
- Purpose-built brick or concrete inspection chamber.
- Precast concrete manhole rings.
- Dedicated sump unit.
Select outfall pipe diameter/gradient
Care should be taken to ensure sufficient capacity.
Highway
Standard outlet formed using two base outlet units (in place of
standard base units) to give full width rectangular outlet 400x275
mm. (shallow and deep base outlet units available). Positioning is
not critical, but should allow access for suction pipe from gully
emptier.
Discharge capacity may be increased by installing more than one
pair of Base Outlet units discharging into the same outfall
chamber.
For larger schemes, chambers to be detailed in accordance with The
Specification for Highway works, clauses 507 and 508. For larger
outfall pipes it may be necessary to incorporate a manhole access
at rear of run.
Clearway/Safeticurb
Select outfall chamber, pipe dimension and pipe gradient to suit
system capacity. Position a silt box top on two courses of
engineering brickwork over the selected outfall chamber/silt trap
to give access (via the silt box lid) for silt removal.
HydroKerb sump unit
With hinged, removable lid for inspection access, is placed over
sump unit in place of standard top units. (See page 143 for
alternative option).
Mini Highway sump unit
With hinged, removable lid for inspection access, is placed over
inflow unit in place of standard top units.
Radii
Highway/Mini Highway:
- To form external radii of 25 metres or less (minimum 6 m),
special radius units should be used (see table below). As these do
not cover all individual radius dimensions, some slight gaps are
required between units as indicated in Highway radii gap widths
table, below.
- For external radii greater than 25 metres, lay straight units
with open joints.
- To form internal radii (minimum 6 metres), use 7/6 internal
radius units.
Clearway/Safeticurb:
- Where necessary, standard (straight) units may be laid to form
radii or bends.
- Safeticurb units: alignment ring within bore acts as a former
for infill mortars to seal joint.
Crossings
Highway/Mini Highway:
- Use crossing base units to carry drainage runs under side
roads/vehicular crossing points. Grid units available.
Safeticurb (DBK unit only):
- To continue linear drainage at road junctions, kerb crossing
points (pedestrian/vehicular), use transition units to reduce kerb
height to road level. These connect with standard grid or slot
units as necessary.
Junctions/sharp bends
Clearway/Safeticurb:
- Use silt box top at outlets or with suitable uPVC pipe fittings
(cut to fit) to form junctions or sharp bends.
Highway radii gaps widths
| Radius (m) |
Radius unit reference |
Top and base gap |
| 6 |
7/6 |
2 |
| 7.5 |
10/8 |
3 |
| 9 |
10/8 |
2 |
| 10.5 |
25/11 |
4 |
| 12 |
25/11 |
1 |
| 15 |
25/11 |
2 |
| 20 |
25/11 |
5 |
| 25 |
25/11 |
7 |
| 26 |
Straight |
7 |