Sitework

Setting out

General principles

Plan for laying to start from an outfall at the lowest point of the system. This ensures self-draining if wet weather occurs during installation.
Use level pins and string lines to ensure correct level and alignment.

HydroKerb:

Excavate trench large enough to allow for concrete bed and haunching, min. 460 mm wide, depth will vary on choice of HydroKerb base unit.

Units should be set out such that the top of kerb is at required level, correct horizontal alignment, radii etc. as shown on setting out drawing (provided by the Engineer), using string lines and pins as appropriate. If radii required is larger than available kerb radius, then use the next size up.

Starting at the outfall, the HydroKerb base units should be laid on a min. 150 mm thick fresh concrete foundation ST4min.
or, alternatively, on a 25 mm thick mortar bed on a previously laid foundation of 150 mm thick concrete. Haunching should be to front and rear of HydroKerb base units 150 mm wide.

Place HydroKerb top unit onto base unit, ensuring that all seatings are clear of concrete and debris to allow for proper location, complete haunchings as required and compact.

Place inspection units at required intervals as work proceeds. This would normally be at the head of the run and at 30 m intervals unless it would coincide with an outlet. Surfacing can be rolled up to units but inlets should be examined afterwards and any surfacing removed from holes.

System should be flushed through after completion.
For optimum laying speed lay a run of base units before laying top units.

Clearway/Safeticurb:

The surface of these systems’ drainage units should be 3-6 mm below the level of the surrounding pavement surface.

After completing base foundations, lay units onto a Class 1 mortar (1:3 cement: sand) bed, adjusting to line and level using a pavior’s maul.
Leave 1mm gap between units to allow for thermal expansion.

If a watertight joint is required, a gun-applied sealant may be applied to the end of each unit.

Clearway grid units
Grid fixing bolts should be tightened to a torque of 20 Nm after installation and whenever grids have been removed for maintenance.

Safeticurb DBA and DBJ slot units
Protect slots from stones during construction. Slot units without iron inserts can be damaged when stones are impacted by vehicle traffic.

Safeticurb DBG and DBJ grid units
Grid fixing bolts should be tightened a minimum of 5 turns after clamping plate has made contact with the soffit of the bore.

Highway/Mini Highway/Highway Ultra (including Porous Asphalt units):
Specially designed lifting tools available to enable units to be placed accurately in position.
Lay units onto a fresh concrete base (see installation design), adjusting to line and level using a pavior’s maul.
Apply gun-applied (see note, below) sealant to the ends of the base outlet unit prior to laying.

Note: Suitable product would be Evo-Stik roof and gutter sealant. Alternatively a trowel applied mastic sealant can be used, e.g. Denso.

Apply gun-applied sealant to the sealant recess in the end of the first standard base unit – lay the unit against the base outlet unit with the sealant recess away from the outlet. Lay subsequent base units, applying sealant to the sealant recess in each, preferably before laying each unit in position.

When a crossfall is required across the top of Highway units, the base units should be laid to this crossfall. Do NOT rely on varying the thickness of mortar in the joints between top and base units.

Use Class 1 mortar (1:3 cement:sand) to fill joints between top and base units. The joint reduces from 20 mm outside to 15 mm inside the unit to ensure complete filling and compaction inside the bore and to avoid cavitation from the water flow.

While laying, the vertical joints between top and bases are unlikely to be maintained over the full length of the run because of minor manufacturing and jointing tolerances. A full top unit cut to suit may be required to complete the run.

Use the specially designed lifting tool to place top units in position, ensuring that the inlet holes at the ends of each unit are correctly aligned. Adjust using a pavior’s maul.

Remove excess mortar from inside bore as each unit is laid.
Seal the pipe bore at each end of the run, either by extending the base and haunch concrete (of the Highway units or any adjacent kerbline), or with engineering bricks surrounded with concrete or by using the Highway base stop end units.

Handling equipment

For appropriate handling and lifting equipment, contact Probst Haldning Equipment on 01939 235325.